Project Overview
Project Cost$150,000,000
LocationSacramento County, CA
DurationSeptember 2004 – Present
Site Area1900 Acres
ClientMetro Air Park, LLC
Approving AgencySacramento County
Funding SourceMello-Roos Bonds
Coordinating Agencies
- U.S. Fish & Wildlife
- CA Department of Fish & Game
- Sacramento County Air Management District
- Sacramento International Airport
- City of Sacramento Fire Department
- State Water Resources Control Board
- Sacramento Regional Transit Agency
- Sacramento Area Sewer District
- Sacramento County Water Agency
- Sacramento County Building Department
- State Department of Public Health
- SMUD
- PG&E
- AT&T
- SureWest Communications
- Caltrans
- Reclamation District 1000
- Natomas Central Mutual Water Company
Get In Touch
Scope of Services
Our Role on This Project
01
Pre-Construction
Oversaw project planning, budgeting, scheduling, value engineering, permitting, utility coordination, easement acquisition, and bid preparation.
02
Construction
Served as Resident Engineer managing RFIs, submittals, change orders, schedules, invoices, utility coordination, SWPPP compliance, HCP compliance, and project reporting.
03
Post-Construction
Managed project closeout including Notice of Completion, retention release, bond release, maintenance bonds, BMP compliance, and final documentation.
Project Statistics
1900-Acre Site Components
- 2,700,000 CY rough grading and earthwork
- 270 CFS storm drain pump station
- Two 20-acre detention basins
- 25,000 LF backbone storm drain system
- Five miles of arterial roadway improvements
- Backbone infrastructure installation
- 13,000 LF trunk sewer pipeline
- 32,000 LF water distribution mains
- 26,000 LF joint utility trench
- 2.5 million gallon welded steel water tank
- 24" water transmission main
- Booster pump station
- 8.75 MGD sanitary sewer lift station
- Twin 16" sanitary sewer force mains
- Jack and bore crossings under Interstate 5 and Highway 99
- Miscellaneous infrastructure improvements