Skip to main content

Raley Field

Project Overview
Project Cost$12,000,000
LocationWest Sacramento, CA
DurationJune 2000 – July 2001
Site Area20 Acres
ClientRiver City Baseball
Approving AgencyCity of West Sacramento
Coordinating Agencies
  • City of West Sacramento Fire Department
  • State Water Resources Control Board
  • Fish & Game
  • PG&E
  • AT&T

Scope of Services

Our Role on This Project

01

Pre-Construction

Assisted with concept planning and selection of consultant team including soils engineer, surveyor, civil engineer, and stadium designer.

02

Construction

Served as Owner’s Representative and Project Manager, managing RFIs, submittals, change orders, schedules, invoices, stakeholder coordination, SWPPP compliance, and weekly meetings.

03

Post-Construction

Managed punch list completion, Notice of Completion, bond releases, maintenance bonds, BMPs, Notice of Termination, and final project closeout.

Project Statistics

20-Acre Site Components

  • Site grading and improvements
  • Underground utilities (sewer, storm drain, water)
  • Dry utilities (gas, electric, fiber optic)
  • Paving
  • Landscaping
  • Hardscape
  • Building foundations
  • Steel structures
  • Plumbing and electrical systems
  • Roofing systems