Project Overview
Project Cost$10,700,000
LocationMountain House, CA
DurationApril 2007 – June 2011
Site Area3 Acres
ClientPCCP Mountain House, LLC
Approving AgencyMountain House Community Services District (MHCSD)
Funding SourcePrivate Funding with Future Reimbursement via Municipal Bonds
Coordinating Agencies
- San Joaquin County Air Management District
- City of Tracy Fire Department
- State Water Resources Control Board
- State Department of Public Health
- San Joaquin County Building Department
- Modesto Irrigation District (MID)
- PG&E
- AT&T
Get In Touch
Scope of Services
Our Role on This Project
01
Pre-Construction
Managed design coordination, budgeting, scheduling, value engineering, constructability review, easement acquisition, utility coordination, permitting, and bid document preparation.
02
Construction
Served as Resident Engineer overseeing RFIs, submittals, change orders, schedules, invoices, soils and survey coordination, special inspections, utility coordination, SWPPP compliance, and progress meetings.
03
Post-Construction
Handled project closeout including Notice of Completion, retention release, bond release, maintenance bonds, BMP compliance, Notice of Termination, and final documentation.
Project Statistics
3-Acre Site Components
- Two 3.7 million gallon concrete water tanks
- Partially subterranean tank structures
- Booster pump station installation